Kariba Dam Wall is safe and professionally maintained

by The Zambezi Society • 26 August 2009

Browse listings

SUMMARY OF TALK GIVEN BY CONSULTANT ENGINEER TERRY KABELL ABOUT
THE SAFETY OF KARIBA DAM
   July 2009 

(Updated March 2014)

Prepared by THE ZAMBEZI SOCIETY

Terry Kabell is a very experienced engineer who spent many years with Water Development in  Rhodesia and then Zimbabwe.  More recently he has worked throughout Africa as a consultant, and has been advising the Zambezi River Authority for some 12 years.  He gave a talk to the History Society in Harare on 6th July 2009 about Kariba Dam as part of the organisation's celebrations that year to mark the 50th Anniversary of the building of the dam.  This is summarised below.

UPDATE:  MARCH 2014:  In view of recent media articles calling into question the safety of Kariba Dam Wall, the speaker has provided us with the following comments further to his original presentation: 

"We get one of these scare stories regularly about every three years.  My view is the same as given in my 2009 talk (see below).  The deep plunge pool was anticipated at design stage, and the configuration of the gates was planned to throw the discharged water far enough downstream of the dam foundations.  The depth of the plunge pool is now more-or-less static at 78m, and is not expected to get deeper in the three gates open scenario.  The potential danger is from scour of the water swirling around in the plunge pool and undercutting softer seams in the rock.  This has to be monitored after periods of prolonged spilling, by use of survey, divers and a remote controlled submarine that takes video pictures.  When necessary, underwater repair and protection work has to be carried out.  As far as I am aware, repairs were last carried out some years ago, but the inspections are still carried out on a regular basis as part of the routine care and maintenance of the dam.  It is obviously essential that this work is always continued.  In fact, periods of spillage should be decreased, now that Zambia has increased their generating capacity and will be taking more water through the turbines.

But in the meantime, it has been suggested that an intervention should be initiated, to adjust the shape of the plunge pool by the excavation of some 250 000m3 of rock.  This would alter the pattern of flow within the pool and could reduce (but not eliminate) the scour.  This excavation work would require a cofferdam between the downstream edge of the pool and the tailrace outlets from the power stations.  The exercise would entail considerable cost, and is not without other hazards. There are differences of opinion on whether this proposal is necessary."

*************************************************************************
Here is a summary of Terry's original presentation in July 2009 on the occasion of the 50th Anniversary of the opening of the Kariba Dam Hydro-Electric Project.

Recent rumours about Kariba being overfull and in danger of collapse are nonsense
Terry began his talk by announcing that recent rumours about Lake Kariba being 110% full and in danger of collapse are nonsense. 

The Lake is currently 82% full (its highest this year being 83%in July 2009).  Up to date information about levels and flows at Lake Kariba and elsewhere on the Zambezi River can be found on the Zambezi River Authority's website at www.zaraho.org.zm : specifically on these links:
Lake Levels:   http://www.zaraho.org.zm/lakelavel.html
River flows: http://www.zaraho.org.zm/flows.html

He affirmed that the dam is in no danger of imminent collapse.  His presentation, based on a variety of sources include the Zimbabwean and Zambian power authorities, the Zambezi River Authority  (ZRA) and a number of highly respected experts worldwide, was, he said, to dispel rumours and to assure people that Kariba Dam, throughout its 50 year history, has been regularly inspected for safety and thoroughly monitored both locally and by international consultants, who have found it to be in a very sound state.

Safety inspections & maintenance
Twice yearly inspections and surveys are carried out on Kariba Dam and every 5 years a special safety inspection is undertaken with experts from French and UK engineering companies who were involved in the orginal design. Other ad hoc inspections are carried out from time to time for specific reasons when required (e.g. the "plunge pool" which has been scoured out of the rock by  the water flowing out of the floodgates).   Records and archives for the dam dating back to its construction have been rigorously kept by these companies and there is no cause whatsoever for alarm.

Continuous annual maintenance is carried out on the dam, especially on mechanical parts such as the spill gates and stop locks.

There are literally hundreds of instruments in the wall which measure stress, any changes or movement in the wall, water pressure, drainage etc.  These are continually inspected, have survived the past 50 years remarkably intact and are still functioning well.  (For example, of the 263 original strain meters buried in the concrete of the dam to measure stress in three dimensions, 214 are still operating perfectly).

In 1997, the World Bank commissioned a special investigation of Kariba Dam prior to giving the go-ahead for the construction of the North Bank (Zambian) power station.  A very thorough and extremely sophisticated computer-based analysis was carried out by international experts and Kariba was given a clean bill of health and declared quite safe!

Lake storage levels
The total catchment area of Lake Kariba covers some 663 000 sq kms.  The biggest inflows of water occur during March/April/May at the end of the rainy season.  Flows from the upper catchment in Angola/Zambia usually reach the lake later than those from the lower catchment area in Zambia/Zimbabwe because of the "sponge" effect of the Barotseland Floodplains in western Zambia which hold rainwater and release it slowly over a period of weeks.  The greatest danger of massive floods is if both catchment area flows arrive in the lake at the same time.

The dam's usual spill rate per floodgate is 1500 cubic metres per second (cumecs).  At capacity  each gate spills 9000 cumecs.  However, the dam was constructed to withstand much greater flows than this & indeed at the height of the 1956 great flood, 16 000 cumecs were recorded!  Overtopping of the dam itself, although catastrophic for downstream communities and damaging to the electrics inside the wall, would not necessarily result in collapse of the dam.

The Zambezi River Authority prefers to control the water-level to a maximum operating level of 1 metre below the roadway on top of the wall - to prevent overtopping and electrical damage. Although the dam has 6 floodgates, they prefer, for various reasons to do with stress levels and potential undercutting, to restrict the spill to 3 open floodgates.  Lake levels are carefully calculated with the potential for rainy-season floods in mind, and water is deliberately drawn down from the lake from October each year in order to make sure there is enough storage capacity to cope with a big flood.  Telemetry stations in the upper Zambezi catchment areas provide ZRA staff with prior warnings of a potential flood situation.   However, nowadays, there is less need for dam spillage than there used to be because of increasing power generation requirements.

An operational mistake in 1997/8 resulted in a potentially dangerous situation because ZRA did not lower the lake level from October as usual.  Fortunately the floods that rainy season were not huge and they were able to get away with it.

Challenges
1.  The south bank of the Kariba Gorge downstream of the dam has been a problem from the time the dam was built.  Although the wall is deeply imbedded into the deep-down solid natural rock of the hillside and has been heavily reinforced by buttresses, the top 30 metres of the hillside is composed of a rock which is weak and has tended to slip - a factor which was exacerbated when the hillside was saturated by rain or spray from the open floodgates.   This was a potentially dangerous situation as land slippage could have blocked the dam's underground tunnels.  Various measures have been taken since 1978 to stabilize the bank and prevent slip, including the construction of drainage channels.  These have been successful.  Careful monitoring continues, but it appears that the bank is no longer a danger.

2.  Spillway and stop beams : there is mechanical and electrical equipment involved with these, which can give trouble if not properly maintained.  The dam was originally designed with just 4  spillway gates each approx. 9 sq m in size.  Two more were added after the big floods of 1956 during construction of the dam.  Regular testing is carried out on the gates and the hoist mechanism which lifts and closes them. Many people do not realize that the dam wall is sealed only on the downstream side, with the interior being water-filled.  The presence of water can cause problems with mechanical and electrical parts and deposits on the concrete surrounding the gates sometimes needs to be removed in order for the mechanism to slide correctly.  There is also a recent issue of concrete swelling (see below) which requires attention if it threatens to impede the gate mechanisms.   In 1998 a complete refurbishment of the dam's electrics was undertaken, with wire cables being replaced and a stand-by generator provided in case of power failure.

3.  Concrete swelling
In the 1980s it was discovered that a chemical interaction between concrete and cement in wet conditions can result in slow, but irreversible  "swelling" of the concrete used in dam building.  Tests were carried out on samples of concrete from Kariba and it was discovered that the dam was indeed swelling at a small, but noticeable rate.  Extra instrumentation was installed and it has been discovered that the crest of the dam is 80mm higher today than when it was first built!  Arch dams like Kariba are naturally a little flexible, and it has been noticed that when the lake levels are low, the dam moves up to 50mm upstream and then back downstream again when it fills!  Furthermore, the dam now tilts slightly (about 10mm) off the vertical in an upstream direction.

One of the problems associated with this is that it can affect the spillgates, stoplocks and moveable parts.  These have to be checked regularly and maintenance carried out (e.g. chipping away of concrete) to ensure that they move freely.

4.  Seismic Activity (earthquakes)
A branch of Africa's famous Rift pattern falls diagonally across the Kariba zone - so the area has some susceptibility to seismic activity.  Since Lake Kariba began filling behind the dam in 1958, many seismic events have been recorded (no less than 1700 between 1959 and 1999).  The biggest ones were early on, as 200 billion tons of extra load was pressed down onto the Earth by the filling waters of the lake. However, most have been very small.  Since 1999 there appears to have been much less action

In 2001, a study of the Kariba area to check seismicity was undertaken by experts.  Four separate seismograph stations were erected at a distance of some 20 kms away from the dam to map seismic activity, which appears to have been decreasing in recent years.  No damage due to seismic activity was seen, even on the problematic South Bank.

5.  The "plunge pool" (below the floodgates)
This big hole scoured into the rock downstream of the dam wall by water released from the floodgates was forseen by the designers of the wall.  Indeed, the floodgates were designed in such as way as to throw the jet of water out so that the resulting "scour" hole would not endanger the foundations of the dam.

In the first 20 years of the dam's history, there was considerable spillage through the floodgates, which which led to the creation of the pool.  Between 1982 and 2000, the floodgates were not used, due to low lake levels.  Since 2000, the gates have been used very little because of power generation on both the Zimbabwean and Zambian sides of the river.

Currently, engineers are concerned that the plunge pool should not be allowed to scour any deeper and that any cut-back or erosion upstream should be avoided, as this would undermine the foundations of the dam.  The pool has been the subject of number inspections (some with divers) and surveys (the latest in 2001) and the profile of the pool has been fully mapped.  Repairs to soft spots have been repaired using underwater concrete.  If the dam is allowed to spill in the next year, the subsequent effects on the plunge pool will be checked and restoration work will be undertaken.

6.  Concrete apron at the foot of the dam
In the last 5-yearly inspection of the dam (in 2005), the concrete apron at the foot of the dam wall was raised as a point for investigation.  This apron was designed to protect the dam from any small spillage or dribbling (as opposed to full flood jets emanating from the spill gates).  It is now underwater because of tailwater coming from the power generating turbines.  Divers investigating its condition had previously reported that it was breaking up and some repairs with underwater concrete had been undertaken.  However, these had not bonded well with the original concrete, and it was decided to undertake an investigation by drying it out and inspecting.

In April 2007, over the Easter weekend, both power stations were shut down for 8 hours and the water from the bottom of the dam was removed to reveal the concrete apron.  Most of the secondary concrete repairs had broken and washed away, but the original concrete, laid in 1956 was found to be in good condition after 50 years!  (What the divers had seen had been the broken up remnants of the original coffer dam - nothing to do with the original apron itself!).

7.  Reinforcing steel within the dam
A further concern raised by the 2005 inspection was the condition of the steel plates imbedded in the wall.  Although the dam looks like solid concrete, the area around the floodgates is in fact largely solid steel plates covered over with a layer of concrete.  Because of the wet conditions prevailing within the wall, there was a chance of corrosion which needed to be investigated.  Inspection windows were cut into the concrete to expose the steel plates and reinforcing bars.  In all cases, the steel was found to be in perfect condition!  The only problem that faced the investigating teams was to ensure that the concrete used to close up the inspection windows was made to a similar strength as that used originally in 1956!

The examples above were given to show the extent to which the authorities ensure that maintenance and corrective measures are undertaken to protect the dam and ensure its safety.

Summary of possible threats
- Ageing and corrosion.  There are many examples of dams which have existed for hundreds of years.  The evidence from inspections so far indicate that Kariba dam is remarkably free of corrosion and is ageing extremely well
- Overtopping.  If this were to occur, it would cause damage and chaos downstream, but it would not necessarily cause the dam to collapse
- Undermining of the foundations.  This is a real threat, but, as outlined above, regular inspections and protective measures and maintenance ensure that the likelihood of this happening is reduced.
- Swelling of concrete.  This is being carefully monitored and corrective measures taken.
- Earthquake.  A very big earthquake could affect the dam.  But it has been designed to withstand such an event.  Most of the seismic events recorded have been small and the indications are that activity has decreased in recent years.

Funding and personnel
The costs of maintaining the dam wall are born by the governments of Zimbabwe and Zambia through the Zambezi River Authority.  There are challenges.  But some 5 years ago, because of the declining economic situation in Zimbabwe, the Authority was authorized to generate its own funds by charging the National power authorities in foreign currency for use of the water passing through their turbines for the production of electricity.  This has enabled the costs of maintenance to be covered without being adversely affected by the recent decline of the Zimbabwe dollar.

The safety of Kariba dam ultimately depends on people.  In the 2005 report on Kariba Dam, the expert consultants wrote this paragraph about the numerous staff responsible for the dam:
"In the consultants' very wide experience of other dams in many countries, it is rare to find such an experienced, stable, dedicated, friendly and unified team".

The Zambezi Society has compiled this summary for wide dissemination so that such interesting and reassuring information can be in the public domain.  We would like to thank Terry Kabell and salute him and the dedicated staff who work to keep Kariba dam safe and generating power!

THE ZAMBEZI SOCIETY 
Conserving the wildlife and wilderness values of the Zambezi River    http://www.zamsoc.org   zambezi@mweb.co.zw

KARIBA DAM 50TH ANNIVERSARY HISTORICAL DVD:   There is a special DVD, containing fascinating historical footage and documentaries about the building of the Kariba Dam (see picture).  You can obtain a copy from Bill Sykes, History Society of Zimbabwe:  E-mail: sykesbill@zol.co.zw

Post a comment

Enter the three characters from the image on the right. This helps prevent automated 'bots' from submitting spam to the site. This field is NOT case-sensitive. If the characters are a bit hard to see, try refreshing the code by clicking the image.

Browse listings

Enter your details below to subscribe to the Wild Zambezi newsletter.

Close

Enter your details below to subscribe to the Wild Zambezi newsletter.

* indicates required